There has been a great deal of discussion about the Superblock proposals within the community recently and the mechanisms required for a proposal to pass. The code has been examined and the following summary has been formed:
  • The amount requested must be 4320 BLOCK or less — Votes in favor must be greater than votes against by at least 10% of the total number of Service Nodes.
  • The proposals that pass are sorted in a descending order list by the sum of yes votes minus no votes. If multiple proposals have an equal sum of yes votes minus no votes, those are sorted randomly. If there are not enough funds remaining in the Superblock for a proposal to be paid out, it is skipped (not paid out), and the next proposal in the list is checked.
  • Multi-month proposals are voted on each month and are treated in the same manner as normal proposals in the ordered list.
    There is also something called a ‘final budget,’ which needs to be submitted between 2880 blocks and 28 blocks before the Superblock. By default, Service Nodes automatically vote yes on final budgets. Moving forward, proposal voting will end 2880 blocks before the Superblock since the final budget locks in the proposal vote counts.
Voting will end on block 472320



Proposal 1: XBridge Team
  • XRouter development
  • XRouter C++ Developer - Juan (538 BLOCK)
  • XRouter C++ Developer - Arturo ($135/hr from Development Fund)
Cost Assessment:
A fixed amount of 676 + 10 BLOCK
A variable amount of $135/hr from Development Fund
Total: 686 BLOCK from Superblock + $135/hr from Development Fund
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Development Fund.


Proposal 2: Development (michael)
  • Wallet redesign
  • Block DX development
  • XRouter development
Cost Assessment:
A fixed amount of 1230 BLOCK
Total: 1230 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Development Fund.


Proposal 3: DXTools (infinity7592)
  • Ledger integration
  • Microservices for DX Explorer
  • DX Testing
  • Trading lib (improvements and doc)
Cost Assessment:
A fixed amount of 375 BLOCK
Total: 375 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Development Fund.


Proposal 4: Marketing (shane)
  • Launch Social Media Teams
  • Seach engine advertising campaigns
  • Launch Coin Portals
  • Produce Blocknet videos
Cost Assessment:
A fixed amount of 640 BLOCK
Total: 640 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Marketing Fund.


Proposal 5: Project Coordinator (hanniabu)
  • API Docs
  • Documentation/Resources
  • Block DX setup automation
  • Developer recruitment
  • Website Specs and Content
  • Assist with daily tasks
Cost Assessment:
A fixed amount of 350 BLOCK
Total: 350 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Ecosystem Growth Fund.


Proposal 6: Support/Test (86b)
  • Support lead / strategy
  • Product analysis
  • Bug reporting
  • Collaborating with other coin teams
Cost Assessment:
A fixed amount of 350 BLOCK
Total: 350 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Development Fund.


Proposal 7: Community Rep (stormingj)
  • Engage with community
  • Relay/voice community concerns
  • Moderate community channels
Cost Assessment:
A fixed amount of 50 BLOCK
Total: 50 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Ecosystem Growth Fund.


Proposal 8: Creative Lead (bob)
  • Graphic Design for marketing agendas
  • Creative consultant
  • Further detailed position description: https://goo.gl/vHhhgs
Cost Assessment:
A fixed amount of 650 BLOCK
Total: 650 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Marketing Fund.


Proposal 9: Social Coordinator (philipmarshall)
  • Maintain the social media profile of Blocknet
  • Ensure communications from the developers and marketing team can be transmitted in a clear and timely manner to the community
  • Participate as part of a coordinated marketing team
  • Respond to the community
  • Continue to contribute to marketing materials and initiatives
Cost Assessment:
A fixed amount of 115 BLOCK
Total: 115 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Marketing Fund.


Proposal 10: Support/Test (aderks)
  • Support for new coins integration
  • Bug reporting
  • Genesis tests
  • Collaborating with other coin teams
Cost Assessment:
A fixed amount of 200 BLOCK
Total: 200 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Development Fund.


Proposal 11: Support/Test (fattox)
  • Support for new coins integration
  • B2B - Communicating with Partner delegates
  • Brand Lead - Involvement with Marketing/SMT initiatives
  • General/Tech support (via ticket-system + social platforms)
  • Further detailed position description: https://goo.gl/KdG84E
Cost Assessment:
A fixed amount of 200 BLOCK
Total: 200 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Development Fund.


Proposal 12: Project Coordinator (baron)
  • Team & Groupwork
  • Documentation/Resources
  • Procedural development & Change Agency (with Arlyn)
  • Intra and Inter-team communication
  • Other recruitment & Training
  • Regional representation
Cost Assessment:
A fixed amount of 300 BLOCK
Total: 300 BLOCK from Superblock
If this proposal passes but is bumped from the Superblock due to there not being enough room, this will be paid out from the Ecosystem Growth Fund.


Total Cost Assessment:
  • XBridge Team - 686 BLOCK + $135/hr from Development Fund
  • Development (michael) - 1230 BLOCK
  • DXTools (infinity7592) - 375 BLOCK
  • Marketing (shane) - 650 BLOCK
  • Project Coordinator (hanniabu) - 350 BLOCK
  • Support/Test (86b) - 350 BLOCK
  • Community Rep (stormingj) - 50 BLOCK
  • Creative Lead (bob) - 650 BLOCK
  • Social Coordinator (philipmarshall) - 115 BLOCK
  • Support/Test (aderks) - 200 BLOCK
  • Support/Test (fattox) - 200 BLOCK
  • Project Coordinator (baron) - 300 BLOCK
If any of these proposals pass but are bumped from the Superblock due to there not being enough room, they will be paid out from the respective listed funds.

Voting will end on block 472320


For instructions on how to vote, see: https://docs.google.com/document/d/1d0AS4lFVB7rkigE5hlVE58wWHO7gQCrNCmatUDRZwRg/preview
avatar
Posts : 42
Join date : 2017-10-22
View user profile

Re: Superblock 475200

on Thu Jun 28, 2018 9:56 am
Proposal 1: XBridge Team
mnbudget vote c0ef91b2922d24210b549ca218ac828eeffd30b220e49d49d66181c5f831e664 yes/no

Proposal 2: Development (michael)
mnbudget vote f7db025223478591883a22b8a52c4b7013e7dd96bee7df746681771cdaf7545e yes/no

Proposal 3: DXTools (infinity7592)
mnbudget vote d7d659bc0d25e50cb0483e26a4f6e2a1aaed2a1b7775fbeacb75665f97acc625 yes/no

Proposal 4: Marketing (shane)
mnbudget vote b6d533a858b78226604c9d7e26e7ee7a969b8cb4f544ff4f08695655925eec62 yes/no

Proposal 5: Project Coordinator (hanniabu)
mnbudget vote a6ba5800c8c3550bcb10cd146d8ee3281b9d3671b3f61c5fa48e67fb64886cc0 yes/no

Proposal 6: Support/Test (86b)
mnbudget vote 94e8ef15cc79e7743c4331fc30b7a3221ba2c8b710bad95e0a9a38134302aaa5 yes/no

Proposal 7: Community Rep (stormingj)
mnbudget vote 881f3a484b5a44317f1cf3c90f44e9f063fa52a3069ccbe0f1ada12f307f77f1 yes/no

Proposal 8: Creative Lead (bob)
mnbudget vote 78b136320683f98d795760f1d0de9fed33799f0e7cba08d61486406237288e5a yes/no

Proposal 9: Social Coordinator (philipmarshall)
mnbudget vote 68c54f0869f3dbf1cdde94ed54142f5dbe482e748da33da0b0031dc742ab7031 yes/no

Proposal 10: Support/Test (aderks)
mnbudget vote 33d3626e8f15096e5f5200da84594e678431b99f80d9add1488d918885b597d9 yes/no

Proposal 11: Support/Test (fattox)
mnbudget vote 165967ea110599277fd5119feae464f19fb0e7206f6f0304273698b5a7f979fe yes/no

Proposal 12: Project Coordinator (baron)
mnbudget vote 15eaf9d464e85cd2301bc9382f9c74d98fba9a487d7a2ead92d3d07377f12b1a yes/no